FOI Request Major Planning Decisions

Request 101001648146

• The average decision time for a major housing development planning application for each financial year since 1999 -2000, including 2016-2017? This would include residential developments of over 4 properties

Response 17-11-2017

Please note: These figures do not account for some of the ‘legacy’ cases where applications were not determined on account of other factors, or in agreement with the applicant. These figures will also include applications for which a processing agreement has been in place and would therefore be taken out of average figures in the Scottish Office returns.

 

Year Number of applications Average decision time (days)
1999/2000 7 166.43
2000/2001 8 170.00
2001/2002 18 104.33
2002/2003 5 187.80
2003/2004 9 574.11
2004/2005 8 229.63
2005/2006 7 528.00
2006/2007 14 282.71
2007/2008 19 460.63
2008/2009 15 535.73
2009/2010 14 469.79
2010/2011 7 568.00
2011/2012 2 1121.50
2012/2013 5 1078.00
2013/2014 4 777.00
2014/2015 2 259.50
2015/2016 3 815.33
2016/2017 3 368.33
Total 150 414.36