FOI Request - Surface Dressing

Request 101000334864

Could you give me records you hold of surface dressing failures over the last 5 years, I was looking for both areas and costs incurred as a result of the failures.

Response 15-04-2015

2014 = 309,911sqm dressed = 1,485sqm remedial = 0.48% of total = £4,200

2013 = 397,110sqm dressed = 218sqm remedial = 0.05% of total = £400

2012 = 366,379sqm dressed = 319sqm remedial = 0.09% of total = £1,000

2011 = 328,660sqm dressed = 6,308sqm remedial = 1.92% of total = £13,300

2010 = 321,292sqm dressed = 0sqm remedial = 0.00% of total = £0

The Moray Council, Roads Service operates a “twin hatted” approach, acting as both Client and (through our own DLO) as Contractor in surface dressing.  The cost of remedial works is borne in full by the Contractor (DLO), from their operating budget and is not separately identified. Therefore the costs shown above are only theoretical, based approximately on contract rates.