FOI Request - Housing Development Delays
Request 101003834871
I would like to request the following data regarding delayed housing developments in Britain:
Please provide a list of housing developments in the area covered by Moray Council that have experienced delays in completion during the period 1 January 2020 to 31st July 2025.
For each delayed development, please provide the following:
• Name and/or address/location of the development
• Planning application reference number
• Originally expected completion date
• Actual or most recent known completion date (if completed or ongoing)
• Status (e.g. not started, in progress, paused, abandoned, completed late)
• Any available reason(s) recorded for the delay
Response 05-09-2025
There has been one delayed project:
Name and/or address/location of the development: Planning application reference number 18/01497/APP
Originally expected completion date: 14/03/2022
Actual or most recent known completion date (if completed or ongoing): 26/04/2023
Status (e.g. not started, in progress, paused, abandoned, completed late): completed late
Any available reason(s) recorded for the delay: Radon protection measures
Please note, the above is from Housing and Property who stated that they can only comment on developments within the Council’s own affordability housing development programme.