FOI Request - Working Hours - Roadworks on Fife Street, Dufftown

Request 101003992946

1. What are the daily working hours?

2. Will there be evening or weekend work to expedite the process, or is it restricted to standard 8:45 am – 5:00 pm hours?

Response 25-05-2026

There are no road works currently being undertaken at Fife Street, Dufftown. The traffic management is in place to protect the retaining wall between the road and the houses to the south of the road from vehicle loading. An investigation is currently underway into the condition of the wall and options that can be implemented to stabilise it. When this work is complete, the preferred option will be implemented, subject to available funding. The working hours for this work is likely to be standard, which is between 7am and 7pm.